Pool construction in Croatia: the complete guide (2026)
The rules that apply from 2026, construction stages and timing, prices and running costs after the build – from the perspective of a team with 800 to 1,000 completed projects between Makarska and Zadar.

Pool construction is not just excavating and pouring the shell – it is a project that covers preparing the documentation, excavation, a reinforced-concrete structure, waterproofing, the lining, a plant room with filtration, and the water and power connections. A family pool with a footprint of up to 100 m² sunk into the ground does not need a building permit, but it does need a main design and a construction start notification. Construction typically takes 6 to 12 weeks.
This guide is written from the perspective of a team with 16 years of experience in the trade, covering the area from Makarska to Zadar through 800 to 1,000 completed projects. We go through what an investor wants to know before the first contract: which paperwork is mandatory under the rules in force from 1 January 2026, which type of pool makes sense for your plot, how long construction takes, what it costs – and what it costs every year after construction. We put particular emphasis on what is different in Dalmatia, because that is where budgets and deadlines most often fall apart.

Does a pool need a building permit?
For the great majority of family pools in Croatia, no building permit is required. The Ordinance on Simple and Other Structures and Works (Pravilnik o jednostavnim i drugim građevinama i radovima, ‘the Ordinance’ below) distinguishes two regimes: a shallow garden pool is built without any documentation, while an in-ground pool of up to 100 m² is built without a permit but in accordance with a main design and with a mandatory construction start notification. The two legal bases are often confused.
Garden pool up to 1 m deep – no permit and no main design
Under Article 3, point 4 of the Ordinance, works to landscape the building plot of an existing structure can be carried out without a building permit and without a main design, including the construction of ‘a garden pool or pond up to 1 m deep measured from the level of the surrounding ground’. The 1 m depth limit applies only to this category – shallow decorative pools and smaller bodies of water that form part of a garden layout.
In-ground pool up to 100 m² – no permit, but with a main design
This is where almost every family pool belongs. Article 4, point 1(c) of the Ordinance provides that an ancillary structure can be built without a building permit, but in accordance with a main design, on the building plot of an existing building, for the needs of that building, namely ‘a pool with a footprint of up to 100 m² sunk into the ground’.
The three conditions are cumulative – all three must be met at the same time:
- A footprint of up to 100 m². The footprint is measured, not the volume.
- The pool must be sunk into the ground. Above-ground and prefabricated designs do not fall under this point.
- It must be located on the building plot of an existing building and serve the needs of that building. If there is no existing building on the plot, this legal basis does not apply.
There is also a related provision, Article 4, point 20, which treats in the same way ‘a pool with a footprint of up to 100 m² sunk into the ground within a building plot or within the area of a campsite development’.
In practice, all the sizes that are built most often are comfortably below the threshold. A 6 × 3 m pool has an 18 m² footprint, 7 × 3.5 m has 24.5 m², the most popular 8 × 4 m has 32 m², 10 × 5 m has 50 m², and even a large 12 × 6 m has 72 m² – still below 100 m².
The construction start notification is mandatory
Article 6, paragraph 3 of the Ordinance states: ‘The investor is obliged to notify the start of construction of the structures referred to in Article 4 of this Ordinance.’ Because an in-ground pool of up to 100 m² falls precisely under Article 4, a construction start notification is mandatory for it. This is the step investors skip most often, because they have heard only the first half of the story – ‘a pool doesn’t need a permit’.
On the other hand, confirmations from public-law bodies in the main design and professional supervision are required under Article 6, paragraphs 1 and 4 only for structures for which a use permit is issued – those intended for carrying out a business activity or those recorded in the cadastre.
The spatial plan overrides the Ordinance
This is the provision that sinks the most projects and is talked about the least. Article 1, paragraph 2 of the Ordinance says that the structures covered by the Ordinance ‘must not be designed, built or carried out if this is prohibited by the spatial plan or is otherwise contrary to the spatial plan’.
The Ordinance therefore exempts you from the building permit, but not from the spatial plan. The distance from the plot boundary, the permitted site coverage and the design requirements are set by the spatial plan in force for your municipality or town, not by the Ordinance. Your first call should be not to a contractor but to the spatial planning department of the competent local authority.
The new Building Act requires the contractor to meet the conditions for carrying out construction activity and to appoint a site engineer and/or works manager who directs the construction and keeps the construction logbook (Articles 21–23). Professional supervision is the general rule for structures for which a building permit is issued (Article 26, paragraph 1).
What you need, depending on the pool type
| Type of works | Building permit | Main design | Construction start notification | Legal basis |
|---|---|---|---|---|
| Garden pool or pond up to 1 m deep from the level of the surrounding ground, on the plot of an existing building | No | No | Not prescribed by Art. 6, para. 3 (which refers to Art. 4) | Ordinance, Art. 3, point 4 |
| Pool with a footprint of up to 100 m², sunk into the ground, on the building plot of an existing building and for the needs of that building | No | Yes – built in accordance with the main design | Yes – mandatory | Ordinance, Art. 4, point 1(c) + Art. 6, para. 3 |
| Pool up to 100 m², sunk into the ground, within a building plot or the area of a campsite development | No | Yes | Yes | Ordinance, Art. 4, point 20 + Art. 6, para. 3 |
| Any of the cases above, if the project is contrary to the spatial plan | Must not be designed, built or carried out – even though the project is listed in the Ordinance | Ordinance, Art. 1, para. 2 |
Another piece of good news for private investors: the Ordinance on the sanitary, technical and hygiene conditions of swimming pool facilities (NN 59/2020) states expressly in Article 2 that it does not apply to pools owned by private individuals that are not intended for public use. Your family pool does not carry the obligations that public pool facilities do. The limit values in that ordinance (pH 6.5–7.8, free chlorine 0.2–1.0 mg/l, turbidity up to 1.0 NTU, redox above 750 mV) are nevertheless a useful technical guide to water quality in a private pool as well. Monitoring of the water in public pool facilities is carried out by the sanitary inspectorate of the State Inspectorate. For the conditions on discharging pool water, check with the competent local utility company (in Split, ViK Split).
Which type of pool should you choose?
In Croatia, three technologies are realistically on offer: concrete (a reinforced-concrete shell cast on site), fibreglass (a ready-made shell that is delivered and lowered into a prepared excavation) and above-ground (freestanding structures of metal, wood or panels). The difference is not just in the price but in how limited you are in the shape, depth and position of the pool.
A concrete pool has no limit on shape or depth. It is built to fit the plot and can have steps, a shallow beach area, a counter-current unit, an overflow edge and built-in seating. We work only on concrete pools, and this is the choice we recommend when the pool is a permanent part of the house and garden. The drawback: it takes the longest and costs the most at the start.
A fibreglass pool is quicker because the shell is ready-made. You are limited to a catalogue of shapes and – which in Dalmatia is often decisive – the shell has to physically reach the plot and be lowered in by crane. On a narrow street in the old part of Trogir, or on a plot reached across someone else’s land, that can be impossible. To be fair: if you have easy access and a simple rectangular shape and want a pool quickly, fibreglass is a legitimate choice and concrete is not automatically ‘better’.
An above-ground pool is the cheapest way in. It is not sunk into the ground, so it does not fall into the category in Article 4, point 1(c) of the Ordinance and is treated differently. It is a solution for temporary use and for budgets where an in-ground pool is not an option.
We cover the detailed comparison of the types, with their advantages and drawbacks, in separate articles: read in-ground vs above-ground pool: which to choose and why and the comparison of concrete, fibreglass and overflow pools.
Skimmer or overflow pool?
The difference lies in the water level and in how the water goes to the filtration. In a skimmer pool the level is a few centimetres below the edge, and the water enters through skimmers in the wall. In an overflow pool the water is level with the edge and spills over the whole perimeter (or one side) into an overflow channel, and then into a balance tank.
An overflow pool has better hydraulics because the surface layer of water – the one with the most dirt in it – is drawn off along the whole length of the edge, not at just two or three points. In return it needs a balance tank, a larger plant room and more precisely executed levels, which also makes it more expensive.
An infinity design is a subset of overflow: only the side facing the view overflows. We have built such pools in Trogir and Okrug Donji – where the plot elevation is right, the result justifies the difference in price. Where it is not, it does not.

What are the stages of pool construction and how long do they take?
Building a concrete pool here typically takes 6 to 12 weeks, depending on size and complexity. The lower end applies to a simple skimmer pool in earth with good access; the upper end to an overflow pool with excavation in rock, demanding lining and additional equipment. The range does not include preparing the main design and the paperwork before the works begin.
| Stage | Approx. weeks | What is actually done |
|---|---|---|
| Preparation (before the start) | — | Checking the spatial plan, main design, construction start notification, contract and start date |
| 1. Excavation and site preparation | 1.–2. | Setting out, excavation, removal of material, compacted gravel sub-base. In rock this stage takes the longest and deviates most from the plan |
| 2. Foundation slab and reinforced-concrete shell | 2.–5. | Reinforcement, formwork, pouring the slab and walls, curing the concrete and stripping the formwork |
| 3. Installations and wall penetrations | 4.–6. | Pipework, skimmers or overflow channel, inlets, underwater lighting, earthing, cabling |
| 4. Plant room | 5.–7. | Filter, pump, valves, automatic controls, disinfection, heat pump if required |
| 5. Waterproofing and substrate preparation | 6.–8. | Levelling, waterproofing system, watertightness test |
| 6. Lining | 7.–10. | PVC liner, ceramic tiles or glass mosaic. Mosaic takes the longest because it is done by hand |
| 7. Filling, commissioning, handover | 9.–12. | Filling with water, balancing the chemistry, trial run of the filtration, user training, documentation and guarantee |
The stages overlap, so the sum of the individual ranges is not the total duration. The sequence is fixed: the lining cannot go on until the concrete has cured, and filling cannot start until the lining is finished.
When to book a slot so the pool is ready for summer
According to the climate normals of the Croatian Meteorological and Hydrological Service (DHMZ) for the Split-Marjan station, the mean monthly air temperature is 19.2 °C in May, 23.4 °C in June and 26.2 °C in July. If you want the pool operating at the start of the season, construction has to finish by the end of May. With a duration of 6 to 12 weeks, that means starting work in March at the latest – and since the main design and construction start notification come before the works, the conversation with the contractor realistically belongs in autumn or early winter of the previous year.
How much does it cost to build a pool?
A concrete skimmer pool of 8 × 4 m typically comes to about €35,000 (excluding the concrete shell) with us. An overflow version of the same size is about 30% more expensive. The realistic minimum budget for starting a concrete pool project is €50,000, because besides the pool itself there are landscaping, a terrace, a fence, lighting and connections – and that is outside our scope. These are all indicative ranges, not a binding quote.
Why the price per m² is misleading
Excavation, the plant room, pipework and connections have a large fixed component that does not grow in proportion to the pool’s surface area. An 18 m² pool needs the same water connection and plant room as a 32 m² one. That is why the price per square metre falls as the pool gets bigger, and why we price by project, not per m².
A second reason: equipment is sized by the volume of water, not by the footprint. An 8 × 4 × 1.5 m pool holds 48 m³, or 48,000 litres; the same footprint with a smaller depth needs a different filter and a different pump. Two pools with an identical footprint can therefore have a significantly different equipment cost.
Flusso ranges and market ranges
| Item | Indicative amount | Source |
|---|---|---|
| Concrete skimmer pool 8 × 4 m | ≈ €35,000 (excluding the concrete shell) | Flusso |
| Concrete overflow pool (same size) | ≈ 30% more than the skimmer pool | Flusso |
| Minimum budget for a concrete pool project | €50,000 | Flusso |
| Vidrepur glass mosaic – material | €30–250/m² | Flusso |
| Mosaic – installation with a basic mosaic, all included | ≈ €160/m² | Flusso |
| Renolit liner | ≈ €110/m² | Flusso |
| Concrete pool – market range per m² | €900–1,250/m² | eMajstor.hr |
| Fibreglass pool with excavation – market range per m² | €780–1,080/m² | eMajstor.hr |
| Concrete pool – overall market range | €25,000–58,800 | Trebam.hr |
| Fibreglass in-ground pool – market range | €13,800–20,000 | Trebam.hr |
| 8 × 4 × 1.5 m pool with PVC liner – market range | €23,000–42,000 | bazenirijeka.com |
| 8 × 4 × 1.5 m pool with ceramic tiles or mosaic – market range | €32,000–60,000 | bazenirijeka.com |
For a full itemised breakdown of prices, read how much it costs to build a pool – prices by type and size, and if you are interested specifically in the most popular size, see the cost of an 8 × 4 m pool, with prices by size.

What is different about building in Dalmatia?
Four things change a pool project on the Dalmatian coast compared with inland Croatia: the ground is often rock, site access is narrow, the air carries salt and the bora wind is a structural and operational factor. Each of them has a direct effect on the price, the schedule or the choice of materials – and none of them can be seen in a photo of the finished pool.
Excavation in rock
Excavation in earth is a predictable job. Excavation in solid rock is not: it needs different machinery, takes longer and produces material that has to be hauled away. In quotes this item usually appears as ‘according to actual conditions on site’ and it is the most common reason why the final bill departs from the estimate. Ask the contractor how rock excavation is charged before you sign, not after the first day of digging.
Site access
A ready-made fibreglass shell has to reach the plot and be lowered in by crane. In old town centres, on steep approaches and on plots reached across someone else’s land, this can be impossible. A concrete pool is more tolerant because the material is delivered in parts, but even then the access determines which machinery can reach the excavation. Checking access is the first thing we do on a site visit.
Salt, climate and season
Proximity to the sea means salt in the air and a greater load on metal parts, lighting and the lining. That is an argument for quality components and for a lining that withstands UV and chemicals – in practice we prefer glass mosaic, which lasts longer than a liner, even though it is more expensive and has to be installed by hand.
The climate, on the other hand, is the biggest asset. According to DHMZ data for Split-Marjan, there are 271.4 hours of sunshine in May, 309.0 in June, 353.3 in July, 328.0 in August and 247.1 in September. The mean air temperature in September is 21.6 °C – higher than in May. September, which many write off, remains a full swimming month with heating.
The bora and uplift
The bora means that covers, awnings and everything around the pool have to be anchored, and that lightweight solutions do not survive. It also means more leaves and dust blown into the water, so more frequent cleaning and a greater load on the filtration than in a sheltered spot.
Uplift is a structural issue: an empty pool in ground with a high water table is exposed to hydrostatic pressure from below. That is why a pool should not be emptied without a reason, and drainage and the method of winterising are agreed at the design stage.
Market context: according to the Croatian Bureau of Statistics (DZS) data on building permits issued in 2025, the projected value of works in Split-Dalmatia County is €640,082 thousand, of which €395,447 thousand is on residential buildings, with 2,481 dwellings. Nationally, 11,733 permits were issued with a value of €7.86 billion, for 21,809 dwellings (+6.9% vs 2024). In terms of contractors’ schedules: demand on the coast is growing, and this shows in the construction calendar.

What equipment should you plan for?
Pool equipment is sized by the volume of water, not by the footprint. The volume determines how large a filter and which pump are needed, and therefore the cost of the plant room. An 8 × 4 × 1.5 m pool holds 48 m³ of water – that is the figure to start the equipment calculation with, not the 32 m² footprint.
Filtration and pump
Here we give an overview; the full treatment – in what order the equipment is assembled, how it is sized and where the limits lie – is in the guide to pool systems and equipment.
The filter and pump are the only equipment that works every day of the whole season. An undersized pump means the water does not pass through the filter enough times a day and the chemistry cannot keep the quality up – a mistake that shows up not in the first year but in the third. An oversized one means needless electricity consumption. That is why we size by volume, using brands we have experience with: Speck for pumps, Astralpool and Zodiac for the rest of the system. These components make up the pool plant room.
Disinfection: salt electrolysis or automatic liquid chlorine dosing
Our practice is tied to volume: up to roughly 100 m³ of water we go with salt electrolysis, and above 100 m³ with an automatic liquid chlorine and pH dosing system. Electrolysis is more pleasant for the user and involves no handling of canisters, but at large volumes an automatic liquid chlorine system gives more stable control. For orientation: an 8 × 4 × 1.5 m pool (48 m³) and a 10 × 5 × 1.5 m pool (75 m³) are in the electrolysis zone, whereas a 12 × 6 × 1.5 m pool with 108 m³ crosses the threshold.
Heating and covers
An Astralpool heat pump for an 8 × 4 pool costs roughly €3,000, and for a 10 × 4 pool about €4,000. With the climate described above, this is the equipment that gives you May and September back. It belongs to the pool heating category.
Covers retain heat and keep dirt out at the same time. A solar cover is about €1,000, a winter cover about €1,500, and a roller cover, depending on the model, €8,000–20,000. In Dalmatian conditions, with the bora and windblown debris, a cover is not a luxury but an item that directly reduces the cost of chemicals and the hours the filtration has to run.
What are the most common mistakes in building a pool?
The number one mistake we find on other people’s pools has nothing to do with the equipment: the height of the pool ends up not matching the house and surroundings. The pool is built correctly, but it is set wrongly in relation to the terrace level, the house entrance or the slope of the garden – so you go down three steps to reach it where you should have approached it on the level, or the edge of the pool cuts the view from the living room. This cannot be fixed afterwards; it is resolved only at the design stage, by measuring levels and checking sight lines from the places where people actually stand.
Other mistakes that follow logically from all of the above:
- A skipped construction start notification. The investor heard that a pool of up to 100 m² needs no permit and concluded that nothing is needed. Article 6, paragraph 3 says otherwise.
- An unchecked spatial plan. The Ordinance exempts you from the permit, but Article 1, paragraph 2 prohibits building contrary to the spatial plan. Checking takes one phone call.
- Comparing quotes of different scope. One includes the lining and equipment, the other only the shell. The price difference then means nothing.
- Equipment sized by footprint. The filter and pump are chosen by volume of water; the same footprint with a different depth is not the same system.
- A budget without the surroundings. Paving, terrace, fence and garden lighting are not part of the pool works with most contractors – including us.
- Adding equipment later. Heating, a counter-current unit or lighting that were not planned before the concrete was poured cost several times more later.
- A contract with no deadline and no description of how rock excavation is charged. On Dalmatian ground this is the item that changes the final amount the most.
How much does pool maintenance cost after construction?
Regular pool maintenance with us runs at €300–400 a month, depending on the size of the pool. This includes checking the condition of the water, cleaning the pool shell and vacuuming, and the servicing needed in the plant room. For comparison, publicly published market ranges for basic maintenance run from €50 to €120 a month, or €600 to €1,400 a year – the difference lies in the scope of the service and in whether it is a service with a call-out to site or do-it-yourself maintenance with bought chemicals.
If you maintain the pool all year round with a service, €300–400 a month comes to €3,600–4,800 a year. Over ten years that is €36,000–48,000 – often more than the construction itself. That is why the cost of ownership, and not only the construction price, has to be part of the decision.
Electricity: calculate in kWh, then multiply by your own tariff
You can calculate the filtration’s consumption yourself, and accurately, before you even build the pool. The formula is simple:
pump power (kW) × running hours per day × number of days in the season = consumption in kWh
Read the pump power from the rating plate or from the data sheet of the model on offer, then multiply the consumption by your own tariff per kWh from your electricity bill. The arithmetic for a 180-day season:
| Pump power | 6 h a day × 180 days | 8 h a day × 180 days | 12 h a day × 180 days |
|---|---|---|---|
| 0.5 kW | 540 kWh | 720 kWh | 1,080 kWh |
| 0.75 kW | 810 kWh | 1,080 kWh | 1,620 kWh |
| 1.1 kW | 1,188 kWh | 1,584 kWh | 2,376 kWh |
| 1.5 kW | 1,620 kWh | 2,160 kWh | 3,240 kWh |
The table is an arithmetical illustration, not a recommendation for an operating regime – the filtration running hours are set by the designer according to the water volume and the load on the pool. The point is to see the order of magnitude before choosing a pump.
Regulated items are added to the energy part of the bill: network use in the white tariff model is €0.065702/kWh in the higher tariff and €0.028689/kWh in the lower tariff, and in the blue model a single €0.052324/kWh, plus a metering-point fee of €1.983 a month and a renewable-energy (OIE) support fee of €0.013239/kWh. On top of these items comes the price of the energy itself under your supply contract, so read the total price per kWh from your own bill.
Practical consequence: running the filtration on the lower tariff in the white model brings the network part of the cost per kWh down to less than half. The setting is made once, in the controller, and works every season.
How do you choose a pool contractor?
Choose a contractor on three things: whether they meet the legal requirements, whether the scope of work in the quote is clearly defined and who will service the pool in five years’ time. A pool is a system that needs maintenance, so a contractor who disappears after handover is more expensive than one who looked more expensive at the start.
Questions to put to every bidder:
- Who is the named works manager, and do they hold a licence? The new Building Act (NN 155/25) requires the contractor to appoint a site engineer and/or works manager who directs the construction and keeps the construction logbook.
- Do you work with an authorised designer for the main design? Without a main design, an in-ground pool of up to 100 m² must not be built.
- Where exactly does your scope of work end? Ask for a list of what is not included, not only of what is.
- How is rock excavation charged? As a fixed sum, per cubic metre or per hour of machinery – and who bears the risk of deviation.
- What is the guarantee and what does it cover? The structure and the waterproofing are what you cannot repair yourself.
- What does service after handover look like, and how quickly do you attend a call-out?
- Which equipment brands do you install, and are you authorised for them? Serviceability and the availability of spare parts depend on this.
- Can I see a completed project in person? A photograph is marketing; a finished pool on site is proof.
You can read more about how we work, from the first site visit to handover, on the pool construction and maintenance page.
Next step
If you are building a pool in 2026, the order of moves is: check the spatial plan with the competent planning department, engage an authorised designer for the main design, submit the construction start notification, and only then choose a contractor and a slot. In the reverse order you lose months.
For a specific estimate we need three pieces of information: the dimensions you want, the type of ground and how the site is accessed. Send them via the contact form and we will get back to you with an indicative range, typically within 24 hours.
Note: all amounts are indicative ranges and are not a binding quote. Legal provisions are cited according to the regulations in force in July 2026; before starting work, check the current version of the regulations and the spatial plan for your plot.
Frequently asked questions
For a pool with a footprint of up to 100 m² sunk into the ground, on the building plot of an existing building and for the needs of that building, a building permit is not required – but the pool must be built in accordance with a main design and the start of construction must be notified (Ordinance on Simple and Other Structures and Works, Art. 4, point 1(c) and Art. 6, para. 3). A garden pool up to 1 m deep under Art. 3, point 4 requires neither a permit nor a main design. In both cases the project must not be contrary to the spatial plan.
A concrete pool typically takes 6 to 12 weeks to build, depending on the size and complexity of the work. This does not include preparing the main design and the construction start notification, which come before the works start. For a pool that is running at the start of the season, work should begin in March at the latest, and the conversation with the contractor in the autumn of the previous year.
A concrete skimmer pool of 8 × 4 m comes to roughly €35,000 (excluding the concrete shell), while an overflow version of the same size is about 30% more expensive. A realistic minimum budget for a whole concrete pool project is €50,000. These are indicative ranges, not a binding quote – the final price depends on the finish, the equipment, the excavation conditions and site access.
It depends on the elevation and view from the plot, not on the budget. If the plot is elevated with an open sea view, an overflow or infinity design justifies the difference in price because the water surface visually merges with the sea. In an urban setting, where there is no such view, a skimmer pool gives the same comfort at a lower price and with a simpler plant room.
Regular maintenance with a technician’s visit runs at €300–400 a month depending on the size of the pool, covering water checks, cleaning the shell, vacuuming and servicing in the plant room. Publicly available market ranges for more basic maintenance are €50–120 a month. Calculate electricity separately: multiply the pump power in kW by the running hours and the days of the season, then multiply the resulting kWh by your tariff.